Table
1.
Preventive Maintenance Checks and Services (PMCS) - Continued.
ITEM
NO.
INTERVAL
ITEM TO BE
CHECKED OR
SERVICED
PROCEDURE
EQUIPMENT
NOT READY/
AVAILABLE IF:
5
Weekly
Primary
Manifold/
Directional
Control Valve
(DCV) Bank
(Figure 5)
Ensure that the seven hydraulic metal tubes connected
between primary manifold and DCV bank are tight and
that there are no leaking fittings.
Any condition would
prevent safe operation of
vehicle.
DCV
BANK
PRIMARY
MANIFOLD
I0005HDC
Figure 5.
Hydraulic Metal Tubes.
6
Weekly
HDC System
Pressure
Transducers
Check that all HDC system pressure transducers are
tightly seated in adapters.
Any condition would
prevent safe operation of
vehicle.
7
Weekly
Perform M9 ACE HDC system Functional Check-Out
pro (WP
0025) . If the HDC system does not pass all
portions of the Functional Check-out procedure, refer
to (WP
0021) and proceed to troubleshoot as applicable.
Any condition would
prevent safe operation of
vehicle.
PMCS MANDATORY REPLACEMENT PARTS
There are no mandatory replacement parts for these PMCS procedures.
END OF TASK