TM 5-4210-249-13&P-1
0090-2
DRAFT
0090
END OF TASK
FOLLOW-ON MAINTENANCE
Remove wheel chocks (TM 9-2320-347-10)
END OF TASK
END OF WORK PACKAGE
TFFT02602
CAUTION
•
Pump must be primed when operating water pump.
Failure to prime pump before
operating water pump may damage equipment.
•
Tank fill & re-circulating line valve must be opened only slightly.
If tank fill & re-
circulating line valve is opened fully, water pump cavitation may occur causing
damage to equipment.
Step 2.
Start engine (TM 9-2320-347-10).
Perform setup for Pumping From Onboard Water
Tank (WP 0085).
Ensure pump is primed (WP 0023).
Push pump operator’s panel
TANK FILL & RE-CIRCULATING LINE valve control OPEN button (WP 0004).
Check if
water pump is excessively noisy.
a.
If water pump is not excessively noisy, fault corrected.
b.
If water pump is excessively noisy, replace water pump (WP 0255).
MALFUNCTION
TEST OR INSPECTION
CORRECTIVE ACTION