INSTALLATION
1.
Install fording cable bracket (Figure 2, Item 6) on surge tank mounting bracket (Figure 2, Item 8) with two
screws (Figure 2, Item 7) and locknuts (Figure 2, Item 9).
2.
Insert control cable (Figure 2, Item 10) and hand control (Figure 2, Item 14) through instrument panel
(Figure
2,
Item
15), lockwasher (Figure 2, Item 17), nut (Figure 2, Item 16), and grommet
(Figure
2,
Item
12) in firewall (Figure 2, Item 13), and tighten nut.
3.
Install control cable (Figure 2, Item 10) on fording cable bracket (Figure 2, Item 6) with clamp
(Figure
2,
Item
5), two screws (Figure 2, Item 4), and locknuts (Figure 2, Item 11).
4.
Install control cable (Figure 2, Item 10) in nut (Figure 2, Item 2) on pressurization valve (Figure 2, Item 3), and
tighten screw (Figure 2, Item 1).
TM 9-2320-272-23-4
0768
0768-4