Table 1. Preventive Maintenance Checks and Services (PMCS) - Continued.
ITEM
NO.
INTERVAL
ITEM TO BE
CHECKED OR
SERVICED
PROCEDURE
EQUIPMENT NOT
READY/AVAILABLE
IF:
44
Weekly
Cooling System
Check for leaks,
damaged fins, loose or
damaged hoses, and
debris or dirt in radiator
fins.
Class III leak is
evident.
45
Weekly
Ether
Quick-Start
Assembly
Inspect ether quick-start
assembly
(Figure 25, Item 1)
mounting for loose
hardware. Check lines,
fittings, and canister for
damage.
Any leak or
reservoir
damage is
evident.
1
Figure 25. Ether Quick-Start Assembly.
EXTERIOR
46
Weekly
Tires
a. Check tire tread
depth. Tread should
not be worn beyond
level of wear bar.
Tire worn to or
beyond wear
bar.
b. Check for correct air
pressure, refer to tire
pressure data
(WP 0003).
47
Weekly
Wheels, Studs,
and Nuts
Ensure all wheel stud
nuts are tight using
wheel stud nut wrench
and handle.
Any wheel stud
is missing or
stud nut is
loose.
48
Weekly
Air System
With air system charged
and engine off, check air
lines and fittings for
leaks and damage.
Any reservoir,
line, or fitting
leaks or damage
is evident.