TM 9-2320-283-20-1
ENGINE.
3-21.
WATER TRANSFER TUBE AND BRACKET REPLACEMENT (Continued).
LOCATION/ITEM
ACTION
REMARKS
C.
INSTALLATION (Continued).
8.
Screw (13) and
Secure item (9), item (10),
Torque to 44-49 lb-ft.
washer (12).
and item (11).
9.
Tube (1), two
Install on item (4) and item
a.
Do not tighten clamps
hoses (3), and
(5).
(2).
four clamps (2).
b.
Install new cable tie
straps to replace any
that were removed in
step 4.
10.
Clamp (15).
Install on item (1).
11.
Screw (14), two
Secure item (15) to item (9).
washers (8),
lockwasher (7),
and nut (6).
12.
Four clamps (2).
Tighten.
NOTE
Follow-on maintenance action required:
Add coolant, and check for leaks and
proper operation (TM 9-2320-283-10).