TM 9-2320-361-24-1
0129 00
0129 00-1/2 blank
FIELD MAINTENANCE INSTRUCTIONS
2-1/2 TON, 6X6, M44A2 SERIES TRUCKS (MULTIFUEL)
TRANSMISSION GEARSHIFT LEVER KNOB AND BOOT REPLACEMENT
REMOVAL AND INSTALLATION
INITIAL SETUP:
Applicable Models
All
Equipment Condition
Parking brake set and wheels chocked
(TM 9-2320-361-10).
Battery ground cable disconnected
(WP 0126 00).
REMOVAL
1.
Rotate gearshift knob (1) counterclockwise, and remove from gearshift lever (3).
2.
Slide boot (2) up and off ball socket pedestal (4) and gearshift lever (3).
INSTALLATION
CAUTION
Use care during installation to prevent sharp edges from
cutting boot.
1.
Slide boot (2), small end facing up, over gearshift lever (3) and slide down to fit over ball socket
pedestal (4) on transmission housing.
2.
Rotate gearshift knob (1) clockwise to install on gearshift lever (3).
3.
Connect battery ground cable (WP 0126 00).
4.
Release parking brake and remove wheel chocks (TM 9-2320-361-10).
1
2
3
4
END OF WORK PACKAGE