MWO-9-2320-272-35-1

MODIFICATION OF 5-TON M939, M939A1, M939A2 SERIES FAMILY OF VEHICLES (FOV)

M939 BRAKE STABILIZATION PROGRAM (RETROFIT OF ANTI-LOCK BRAKE SYSTEM (ABS) FOR M939 FOV); MODIFICATION WORK ORDER

JANUARY 2007
CHANGE 1

  MWO-9-2320-272-35-1 - Page 35 of 109

MWO 9-2320-272-35-1
33
Section V.
INSTALLATION INFORMATION
1.
DATE INSTALLED
– Annotate the date the ABS MWO was installed.
2.
INSTALLING TECHNICIAN
– Annotate the last name of the technician who applied the ABS MWO.
If multiple technicians work on different parts of the application, annotate the Lead Mechanic’s name.
3.
KIT SHIPPING CONTROL NUMBER
– Annotate the Vendor’s Shipping Control Numbers from the
Primary and Stand-Alone Kit containers. These numbers should begin with a prefix of “P” and “S”
respectively. The assigned number following the prefixes should match with one another.
4.
INSTALLATION HOURS
– Annotate the hours taken to install the ABS MWO from the appropriate
vehicle listed in table A.
5.
TIRES REPLACED
– Annotate if tires were replaced. (Basic models only.)
6.
APPLICATION SITE
– Enter the depot or National Guard site where the ABS MWO application was
performed.
7.
INSTALLATION NOTES
– Annotate here any problems that materialized during the actual ABS
MWO application that could not have been identified during the preinspection checks.
8.
ROAD TESTED
– Annotate by checking the block that the vehicle has been tested successfully.
9.
DATABASE UPDATED
– This block is checked when the information on this checklist has been
updated in the provided database. If that can not be accomplished, then the “NO” block must be
checked.
Section VI. IN-PROCESS/FINAL INSPECTION
1.
ABS MWO COMPONENTS QA CHECKS (a through l)
– Annotate by initialing the block
associated with the item to be inspected.
2.
PASS QA/INSPECTION
– Annotate by checking this block when all components and associated
hardware for proper installation has been made.
3.
PRE-EXISTING FAULTS
– Annotate any checks that could not be performed due to previously
identified faults. Complete and attach FORM TRK 1204-1, 16 Apr 02 (Attachment A).
4.
NON ABS DEFICIENCIES
– Annotate any deficiencies found during application that do not effect
ABS but do effect vehicle braking.
5.
QA INSPECTOR/DATE
– The QA inspector will sign, date, and print his name acknowledging that a
proper inspection has been conducted on the vehicle and that the ABS MWO application meets the
quality criterion and is ready for issue.
6.
SITE SUPERVISOR/DATE
– The site supervisor will sign, date, and print his name acknowledging
that a proper inspection has been conducted on the vehicle and that the ABS MWO application meets
the quality criterion and is ready for issue.
7.
UNIT REP/POC
– The Unit Representative/POC will sign, date and print his name acknowledging
that a proper inspection has been conducted on the vehicle and that the ABS MWO application meets
the quality criterion and is ready for issue.


Back to Top