TB-9-2350-277-40-P-2

CARRIER, PERSONNEL, FULL TRACKED, ARMORED M113A3

TECHNICAL BULLETIN; INSTALLATION OF CREW II MODIFICATION KIT PART 2 OF 4

JUNE 2009

  TB-9-2350-277-40-P-2 - Page 15 of 100

TB 9-2350-277-40&P-2
INTRODUCTION
0001 00
0001 00-1
PURPOSE
The purpose of this technical bulletin (TB) is to provide instructions and guidance on the method of
modifying the M113A3 Armored Personnel Carrier for Crew II.
It further provides instruction on the
installation of the Crew II modification kit P/N 12498026.
The Crew II modification kit provides
mounting for the next generation of improvised explosive device (IED) jammers.
The modular Crew II
“plug and play” design, allows the main line replaceable unit (LRU), FRF105C dual antenna, and the
remote control unit (RCU) to be utilized by any Heavy Brigade Combat Team (HBCT) vehicle.
The
M113A3 location was chosen to provide the least impact on mission requirements, for example the
commander’s cupola with .50 cal must rotate 360°; however, care must be taken when operating any
weapons towards the right rear as the antenna is fixed in that position.
GENERAL
1.
Priority.
This bulletin is classified NORMAL.
2.
End item(s) to be modified.
This TB applies to the M113A3, Armored Personnel Carrier, 2350-
01-219-7577, P/N 8750170.
3.
Module(s) (components, assemblies, subassemblies, boards, and cards) to be modified.
Not
applicable.
4.
Parts to be modified.
Vehicle Hull and Engine Compartment Cover (P/N 12369630) will be
reworked.
5. Application.
a. Time compliance schedule.
Not applicable.
b.
Lowest level of maintenance authorized to apply this modification.
The lowest level of
maintenance authorized to perform installation described by this TB is Sustainment.
c.
Work force and man-hour requirements for application of the modification to a single unit, end
item, or system.
A mechanic and helper require approximately 4 man-hours to install.
d.
Modifications to be applied to or concurrently with the application of this kit.
Not applicable.
e.
Additional information deemed necessary to assist in the application of this modification.
Kit
application will be concurrent with other depot overhaul/conversion programs, as applicable.
6.
Technical publications affected/changed.
The installation will be supported by TM 9-2350-277
series technical manuals with the upcoming Change 6.