CONFIGURE BAP HOLD-DOWN LOCKS - Continued
Table
2.
BAP Hold-Down Locks Checklist - Continued.
Load BAP
From Ground
Unload BAP
to Ground
Transport
Mode
Transload
BAP to Trailer
Transload
BAP to Vehicle
Notes:
1.
Refer to figure below for location of BAP hold-down locks on vehicle.
SHOWN WITHOUT BAP INSTALLED
FOR CLARITY
BAP HOLD-DOWN
LOCKS
Figure 2.
BAP Hold-Down Locks Checklist.
2.
Winch frame locking levers - UP position is locked to the BAP, DOWN position is locked to the LHS
hook arm.
3.
Jaw and latch assembly are shown on page 1-11 of TM 9-2320-425-10 or TM 9-2320-435-10.
4.
Not applicable for empty BAP (no bay uploaded).
5.
ENGAGED for empty BAP.
6.
Release hydraulic pressure on transload rollers to seat BAP fully on trailer.
7.
Moved to the fully stowed position after BAP is fully loaded on vehicle.
8.
Ramp bay launch requires center roller to be in up position.
9.
Winch frame locking levers and hydraulic hoses are returned to stowed position or up after the winch
cable and hook are removed from the bay for launch.
10. LHS PMCS requires use of BAP lock checklist if BAP is loaded.
11. Ramp and bay locks are checked according to appropriate.
END OF TASK
END OF WORK PACKAGE
TM 5-3990-263-13&P
0015
0015-4