TM-5-3990-263-13-P

PALLET, ADAPTER, BRIDGE, M15

TECHNICAL MANUAL; OPERATOR AND FIELD MAINTENANCE MANUAL INCLUDING REPAIR PARTS AND SPECIAL TOOLS LIST (RPSTL)

APRIL 2012

  TM-5-3990-263-13-P - Page 211 of 728

OPERATOR MAINTENANCE
MANUALLY UNLOADING BRIDGE ADAPTER PALLET (BAP) TO THE GROUND
INITIAL SETUP:
Personnel Required
(2)
References
TM 9-2320-425-10 (WP
0076)
TM 9-2320-435-10 (WP
0076)
PERFORM PROCEDURE
NOTE
The following manual mode operations using the cab control box are to be performed only
when the normal AUTO mode electric circuit is malfunctioning.
1.
Secure winch frame to the BAP and ensure two winch frame locking levers (Figure 1, Item 1) are in the up
position.
1
2
Figure 1.
Secure Winch Frame.
2.
If locking levers (Figure 1, Item 1) are not up:
a.
Remove lockpin (Figure 1, Item 2) from each locking lever (Figure 1, Item 1).
b.
Swing locking lever (Figure 1, Item 1) to the up position.
c.
Insert lockpin (Figure 1, Item 2) into locking lever (Figure 1, Item 1).
3.
If the BAP is loaded, inspect load and ensure it is secure.
4.
Connect two hydraulic hoses (Figure 2, Item 3) to the stowed location connections (Figure 2, Item 4).
TM 5-3990-263-13&P
0018
0018-1


Back to Top