INSTALLATION - Continued
19.
Install air hose (Figure 4, Item 11) and clamp (Figure 4, Item 14) to fitting (Figure 4, Item 15) and tighten clamp
(Figure 4, Item 14).
20.
Install coupling (Figure 4, Item 13) to BAP frame.
21.
Install fitting (Figure 4, Item 8) and elbow (Figure 4, Item 12) to coupling (Figure 4, Item 13).
22.
Install fitting connector (Figure 4, Item 10) on end of air hose (Figure 4, Item 11) to elbow (Figure 4, Item 12).
23.
Install fitting connectors (Figure 4, Items 5 and 6) and ferrules (Figure 4, Item 9) on each end of tubing (Figure
4, Item 4).
24.
Install fitting connectors (Figure 4, Items 5 and 6) on each end of tubing (Figure 4, Item 4) to fittings (Figure 4,
Items 7 and 8).
NOTE
Install loop clamps as noted prior to removal.
All loop clamps are installed the same way, only one clamp setup shown.
25.
Install loop clamp (Figure 4, Item 3) on tubing (Figure 4, Item 4) and BAP frame with lockwasher (Figure 4,
Item 2) and nut (Figure 4, Item 1).
END OF TASK
FOLLOW-ON MAINTENANCE
1.
Install BAP front pin lock guard plate. (WP
0052)
2.
Install BAP control valve. (WP
0062)
3.
Load BAP onto Transporter and connect air system. (WP
0005)
4.
Check air system for leaks.
END OF TASK
END OF WORK PACKAGE