TM 5-4210-249-13&P-3
0483-4
DRAFT
0483
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
NOTE
Tighten screws equally on each side of clamp.
5.
Install clamp (3) on pipe (5) and fitting (4) with two nuts (1) and screws (2).
END OF TASK
FOLLOW-ON MAINTENANCE
1.
Install piping heat trace (if removed) (WP 0606)
2.
Install plumbing insulation (if removed) (WP 0607)
3.
Install pump house panel(s) (if removed) (WP 0540)
END OF TASK
END OF WORK PACKAGE
TFFT00635