INSTALLATION
NOTE
If new valve is being installed, use fittings from old valve.
Wrap all male pipe threads with antiseize tape before installation.
1.
Position double check valve No. 5 (Figure 2, Item 4) against frame rail (Figure 2, Item 2) and install with screw
(Figure 2, Item 1) and locknut (Figure 2, Item 3).
2.
Connect treadle valve control line (Figure 2, Item 7) to valve adapter tee (Figure 2, Item 8).
3.
Connect double check valve No. 2 control line (Figure 2, Item 6) to bushing (Figure 2, Item 5).
4.
Connect secondary relay valve control line (Figure 2, Item 10) to valve elbow (Figure 2, Item 9).
5.
Connect double check valve No. 1 output line (Figure 2, Item 11) to valve elbow (Figure 2, Item 12).
6.
Connect primary relay valve control line (Figure 2, Item 14) to valve adapter tee (Figure 2, Item 13).