5-41. LOAD HANDLING SYSTEM (LHS) LOAD CONTROL VALVE MAIN FRAME
REPLACEMENT (CONT).
NOTE
Both load control valves are removed the same way.
Left side (outside) load control valve controls loading.
Right side (inside) load control valve controls unloading.
(3)
Position drain pan under load control valves (7).
(4)
Remove load control valve (7) from hydraulic manifold (8).
(5)
Remove preformed packing (9), backup ring (10), two backup rings (11), preformed packing (12),
and preformed packing (13) from load control valve (7). Discard preformed packings and backup
rings.