2 in. (6.7 m) above the loading area. Failure to conduct a site survey
could cause the vehicle to slip, turn over, crash into an obstruction,
or contact power lines. Failure to comply may result in injury or death
to personnel.
Unloading the BAP without disengaging hold-down locks may result
in injury or death to personnel.
Water velocity should not be greater than 8 ft. (2.4 m) per second.
Refer to TM 5-5420-290-12 for water velocity requirements for all
launch conditions. Failure to comply may result in injury or death to
personnel.
1.
A site survey must be conducted to ensure the site meets the criteria cited in the warning
above.
OPERATION
NOTE
This procedure is a two soldier task.
In case of emergency while the remote control is in use, push the
emergency stop switch to shut down operation of the LHS.
1.
Secure the BAP to the LHS. Ensure both BAP hold-down lock handles (1) are pushed
in.