TM 9-2320-362-14&P
4-8. CIRCUIT BREAKER REPLACEMENT (COnt’d)
1.
Install bus bar (19) on load side of circuit breaker (18) and
secure with two lockwashers (22) and screws (21).
2.
Install bus bar (11) on line side of circuit breaker (18) and
secure with washer (10), lockwasher (9), and screw (8).
3.
Install circuit breaker (18) into power interface box (4).
4.
Install boot (1) and guard (2) onto power interface box (4) and
secure with four washers (24), lockwashers (25), and screws (26).
5.
Secure bus bar (11) to terminal 11E4 (3) with washer (15),
lockwasher (16), and nut (17).
6.
Secure wire assembly lead (13), bus bar (23), and bus bar (19),
with washers (14), screw (12), and nut (20).
7.
Install gasket (5) and cover (7) on power interface box (4) and
secure with sixteen screws (6).
4-6