TM-9-2320-365-20-3

M1078 SERIES, 2 1/2-TON, 4 X 4, LIGHT MEDIUM TACTICAL VEHICLES (LMTV)

TECHNICAL MANUAL; MAINTENANCE INSTRUCTIONS; UNIT MAINTENANCE; VOLUME NO. 3 OF 5

FEBRUARY 2006
CHANGE 3

  TM-9-2320-365-20-3 - Page 329 of 1268

TM 9-2320-365-20-3
Change 2
7-87
b.
Installation.
(1)
Remove cover (1) from speedometer (2).
(2)
Set dipswitches 3,6,7, and 9 in the down position.
(3)
Set dipswitches 1,2,4,5,8, and 10 in the up
position.
(4) Position speedometer (2) in instrument panel
assembly (3) with retaining ring (4) and two self-
locking nuts (5).
(5) Tighten two self-locking nuts (5) to 9 lb-in. (1 N•m).
(6) Install two protective caps (6) on speedometer (2).
(7) Connect connector PX8 (7) on speedometer
connector (8).
(8) Connect connector clamp (9) on speedometer
connector (8).
c.
Follow-On Maintenance.
(1) Install instrument panel assembly (para 7-15).
(2) Check gage(s) operation (TM 9-2320-365-10).
End of Task.
CAUTION
Ensure dipswitch settings are correct.
Failure to comply may result in inaccurate
speedometer readings.
NOTE
Perform
steps
(1)
through
(3)
on
speedometer.
NOTE
Note position of speedometer prior to
installation.
NOTE
Install plastic cable ties as required.