TM 9-2320-366-20-3
7-20
Change 2
7-5.
100 AMP VOLTAGE REGULATOR REPLACEMENT
This task covers:
a. Removal
b. Installation
c. Follow-On Maintenance
INITIAL SETUP
Equipment Conditions
Cab raised (TM 9-2320-366-10-1).
Batteries disconnected (para 7-57).
Tools and Special Tools
Tool Kit, Genl Mech (Item 46, Appendix C)
Wrench, Torque, 0-200 lb-in. (Item 59, Appendix C)
Socket Set, Socket Wrench (Item 34, Appendix C)
Materials/Parts
Dispenser, Pressure Sensitive Adhesive Tape
(Item 20, Appendix D)
Lockwasher (2) (Item 104, Appendix G)
Nut, Self-Locking (Item 143, Appendix G)
Nut, Self-Locking (Item 144, Appendix G)
Sealing Compound (Item 59, Appendix D)
Tape, Insulation Electrical (Item 68, Appendix D)
Tie, Cable, Plastic (Item 69, Appendix D)
a. Removal.
(1)
Lift dust boot (1) on terminal lug TL35 (2).
(2)
Remove self-locking nut (3), washer (4), and terminal
lug TL35 (2) from voltage regulator (5).
Discard self-
locking nut.
(3)
Lift dust boot (6) on terminal lug TL110 (7).
(4)
Remove self-locking nut (8), washer (9), and terminal
lug TL110 (7) from voltage regulator (5).
Discard
self-locking nut.
NOTE
Tag wires and connection points prior to
disconnecting.
NOTE
Perform steps (3) and (4) on vehicles
equipped with alternator P/N N1506-1
(12420852).