TM-9-2320-387-10

TRUCK, UTILITY: S250 SHELTER CARRIER, 4X4, M1113

OPERATOR’S MANUAL

OCTOBER 2001
CHANGE 1

  TM-9-2320-387-10 - Page 133 of 277

TM 9-2320-387-10
Change 1
2-85
1
2
3
b. Towing Vehicle from Front (Front Wheels Up).
NOTE
• Towing operations for M1113 and M1114 are basically the same.
• Ensure that towbar is connected to towing brackets as shown in
illustration.
(1)
Attach towbars (2) to brackets (10) and to wrecker towing pintle.
CAUTION
• Ensure that wrecker hoisting boom and hook are centered over the
lifting shackles. Failure to do this may result in difficult turning
during towing operations.
• Ensure safety chain is connected correctly to vehicles equipped with
a front winch. Failure to do so may result in damage to front winch.
(2)
Install chain assembly (8) through lifting shackles (7) and attach chain
assembly (8) to the wrecker’s hoisting hook (9).
(3)
Secure safety chain (5) to towed vehicle’s frame and to wrecker directly
behind the bumper. Let safety chain (5) dip to about 1 ft (30.5 cm) from the ground.
9
8
7
2
5
10
6
5
4


Back to Top