15-l 7. RIGHT INTAKE MANIFOLD REPLACEMENT
This task covers:
a. Removal
b. Installation
INITIAL SETUP:
Tools
General
mechanic’s tool kit:
automotive (Appendix B, Item 1)
Materials/Parts
Equipment Condition
l
Air horn removed (para. 3-14).
l
Intake crossover removed (para. 15-20).
l
CDR valve and bracket removed (para. 3-9).
l
Wastenate actuator removed (para. 15-19).
Intake manifold gasket (Appendix G, Item 75)
Manual References
TM 9-2320-387-24P
Maintenance
Level
Direct support
a. Removal
1.
Remove eight intake manifold studs (2) from intake manifold (I).
2.
Remove intake manifold (1) and gasket (4) from cylinder head (3). Discard gasket (4).
3.
Clean mating surfaces of cylinder head (3) and manifold (1).
b. Installation
1.
Install gasket (4) and intake manifold (1) on cylinder head (3) with eight studs (2).
2.
Tighten studs (2),
beginning
at center of intake manifold (1) and working toward
(41 N-m).
ends, to 30 lb-R
FOLLOW-ON TASKS:
l
Install wastegate actuator (para. 15-19).
l
Install CDR valve and bracket (para. 3-9).
l
Install intake crossover (para. X-20).
l
Install air horn (para. 3-14).