TIRE AND WHEEL ASSEMBLY- CONTINUED
ACTION
LOCATION
ITEM
REMARKS
INSTALLATION - CONTINUED
NOTE
Lugbolts (7) are marked R. or L. in direction of forward wheel rotation. To tighten stud
nuts (6) on right side, turn clockwise. To tighten stud nuts (6) on left side, turn
counterclockwise.
9.
Six stud nuts (6)
Screw onto Iugbolts (7), and tighten in
the
10.
Side of frame (3)
Axle (4)
a.
where tire and wheel
b.
assembly is being
removed
sequence shown using stud nut wrench.
Take trestles out from under axle (4).
Lower jack until inner tire and wheel
assembly (5) rests on the ground.
11.
Lugbolts (7)
Six stud nuts (6)
Using stud nut wrench, tighten as much as
possible in sequence shown below.
NOTE
Have Organizational Maintenance tighten stud nuts to 400 to 425 ft-lb (540-560 Nm) of
torque as soon as possible, with outer tire and wheel assembly removed.
12.
Axle (4)
Raise jack until inner tire and wheel
assembly (5) is off of ground.
TA231223
3-15


Back to Top