TM-9-2330-227-14-P

SEMITRAILER, VAN: SHOP, 6-TON, SINGLE AXLE, M146

TECHNICAL MANUAL; OPERATOR’S, ORGANIZATIONAL, DIRECT SUPPORT, AND GENERAL SUPPORT MAINTENANCE (INCLUDING REPAIR PARTS AND SPECIAL TOOLS LIST)

JUNE 1985

  TM-9-2330-227-14-P - Page 72 of 576

TM 9-2330-227-14&P
TIRE AND WHEEL ASSEMBLY - CONTINUED
ACTION
LOCATION
ITEM
REMARKS
INSTALLATION - CONTINUED
13.
14.
15.
16.
Six stud nuts (1)
Outer tire and
Place on stud nuts (1).
wheel assembly (2)
NOT E
Stud nuts (1) are threaded R. or L. in direction of forward wheel rotation. To tighten
lug nuts (3) on right side, turn clockwise. To tighten lug nuts (3) on left side, turn
counterclockwise.
Stud nuts (1)
Six lug nuts (3)
Screw onto stud nuts (1), and tighten in
the sequence shown below using lug nut
wrench.
Side of frame (4)
Axle (5)
Lower jack, take out from under
where tire and wheel
axle (5), and stow.
assembly is being
removed
Six stud nuts (1)
Six lug nuts (3)
a. Using lug nut wrench, tighten as much
as possible in sequence shown below.
b. Put chock blocks in place for tire and
wheel assembly installed (page 2-24).
NOT E
Have Organizational Maintenance tighten lug nuts to 400 to 425 ft-lb (540-560 Nm) of
torque as soon as possible.
NOT E
FOLLOW-ON MAINTENANCE: Install spare tire and wheel assembly (page 3-17).
TASK ENDS HERE
TA231224
3-16


Back to Top