0373
9.
Loosen connector (29) and remove wires (30) from connector (29).
10. Loosen connector (31) and remove wire (32) from connector (31).
NOTE
Both relays are removed the same way.
Bottom relay shown.
11. Remove two screws (33), washers (34), and relay (14) from circuit breaker box (35).
12. Remove four screws (36), washers (37), and circuit breaker box (35) from vehicle.
END OF TASK
INSTALLATION
NOTE
Both relays are installed the same way.
Bottom relay shown.
Install cable ties as required.
1.
Install circuit breaker box (35) on vehicle with four washers (37) and screws (36).
2.
Install relay (14) on circuit breaker box (35) with two washers (34) and screws (33).
3.
Install wires (32) in connector (31).
Do not tighten connector (31).
4.
Install wires (30) in connector (29).
Do not tighten connector (29).
5.
Install nine wires (28) in connectors (27).
Do not tighten connectors (27).
6.
Install three wires (26) in connectors (25).
Do not tighten connectors (25).
7.
Install wire (24) on bus bar (22) and tighten screw (23).
8.
Install eight wires (21) on bus bar (22) and tighten eight screws (20).
9.
Install wire (19) on bus bar (17) and tighten screw (18).
10. Install six wires (16) on bus bar (17) and tighten six screws (15).
11. Install four wires (13), (12), (11), and (10) on relay (14) with four screws (9) and (8).
12. Install four wires (6), (5), (4), and (3) on relay (7) with four screws (2) and (1).
13. Tighten 14 connectors (25), (27), (31), and (29).
END OF TASK
FOLLOW-ON MAINTENANCE
Install 120-Volt circuit breakers (WP 0360)
END OF TASK
END OF WORK PACKAGE


Back to Top