FUEL SHUTOFF CABLE ASSEMBLY REPLACEMENT (Sheet 1 of 13)
PPOCEDURE INDEX
PROCEDURE
PAGE
Removal
Installation
7-365
7-371
TOOLS:
5/8 in. open end wrench
7/16 in. socket with 1/2 in. drive
7/16 in.
open
end
wrench (2
required)
1/2 in. open end wrench (2 required)
9/16 in. open end wrench
3/4 in. open end wrench
15/16
in.
open
end
wrench
(2 required)
Ratchet with 1/2 in. drive
Putty knife
Slip joint pliers
Screwdriver flat tip
SUPPLIES:
Bushing
Cotter Pin
Packing
Wire (8 to 10 ft) (Item 62, Appendix D)
Adhesive (Item 4, Appendix D)
Grommet
Lockwashers
PERSONNEL: Two
REFERENCE:
TM 5-5420-202-10
PRELIMINARY PROCEDURES:
Remove powerplant (page 5-2)
Remove fuel shutoff handle from bracket (page 7-171)
Go on to Sheet 2
4-42
7-364
Change 5
TM 5-5420-202-20-2
Remove subfloor access cover, directly in front of
operator's seat (page 17-8).