INSTALLATION
1.
Install washer (Figure 5, Item 13) and crank (Figure 5, Item 14) on top frame (Figure 5, Item 11) and swivel
nut (Figure 5, Item 16) with pin (Figure 5, Item 15).
2.
Apply light coat of GAA grease to eight strut bushings (Figure 5, Item 3) and torque rod (Figure 5, Item 8).
3.
Install lower strut (Figure 5, Item 4) on top frame (Figure 5, Item 11) with two screws (Figure 5, Item 5),
lockwashers (Figure 5, Item 9), and nuts (Figure 5, Item 10).
NOTE
Torque rod can be installed through one side only.
4.
Install sleeve (Figure 5, Item 12), two springs (Figure 5, Item 2), and upper strut (Figure 5, Item 1) on top frame
(Figure 5, Item 11) with torque rod (Figure 5, Item 8), two lockwashers (Figure 5, Item 7), and nuts
(Figure
5,
Item 6).
TM 9-2320-272-23-4
0582
0582-10