Table 1.
PMCS - WEEKLY - Continued
Item
No.
Interval
Item to
be
Checked
or
Serviced
Procedure
Equipment
Not Ready/
Available If:
NOTE
•
TELESCOPE and HOIST
levers should be
operated at the same
time.
•
Crane movement from
one lever may be slower
than the other when
operating two levers
together.
(3) Move TELESCOPE con-
trol lever to OUT position
to extend boom while
moving hoist control lev-
er to DOWN position to
pay out cable.
Extensions
do not come
out.
TELESCOPE
CONTROL
LEVER
HOIST
CONTROL
LEVER
CABLE
Figure 25.
(4) Check first, second, and
third stages of boom for
broken welds or obvious
damage.
There are
broken
welds or ob-
vious dam-
age to
boom.
TM 9-2320-343-10
0145
0145-44