TM-9-2320-346-10

TRUCK, COMMON BRIDGE TRANSPORT (CBT), 8X8 M1977A4 W/WINCH AND M1977A4 W/O WINCH

TECHNICAL MANUAL; OPERATOR'S MANUAL

OCTOBER 2008

  TM-9-2320-346-10 - Page 330 of 1184

2 in. (6.7 m) above the loading area. Failure to conduct a site survey
could cause the vehicle to slip, turn over, crash into an obstruction,
or contact power lines. Failure to comply may result in injury or death
to personnel.
Unloading the BAP without disengaging hold-down locks may result
in injury or death to personnel.
Water velocity should not be greater than 8 ft. (2.4 m) per second.
Refer to TM 5-5420-290-12 for water velocity requirements for all
launch conditions. Failure to comply may result in injury or death to
personnel.
1.
A site survey must be conducted to ensure the site meets the criteria cited in the warning
above.
OPERATION
NOTE
During all vehicle operations, the operator will drive and be responsible
for the operation of the LHS cab control box. The assistant acts as a
ground guide and will be responsible for directing the operator using hand
signals, operating the remote control unit and winch, and assisting the
operator as needed.
1.
Drive vehicle to unloading area, and stop with rear of vehicle about 16 ft. (4.9 m) in front
of where rear of NATO flatrack is to be set on the ground.
TM 9-2320-346-10
0043
0043-2


Back to Top