TM 9-2320-366-34-2
Change 2
13-369
(9)
Position two bolts (13) and self-locking nuts (14) in
front lifting bracket (15).
(10) Tighten two self-locking nuts (14) to 210-225 lb-ft
(285-305 N
•
m).
c. Follow-On Maintenance.
(1)
Install hydraulic reservoir, if equipped (TM 9-2320-
366-20-5).
(2)
Install tool box (TM 9-2320-366-20-4).
(3)
Install hydraulic manifold (TM 9-2320-366-20-5).
(4)
Install fuel tank (TM 9-2320-366-20-3).
(5)
Install Material Handling Crane (MHC) (para 16-2).
(6)
Install transmission auxiliary oil cooler (TM 9-2320-
366-20-4).
(7)
Install cargo bed (para 15-9).
End of Task.