TM 9-2330-227-14&P
AIR LINES AND FITTINGS
This task covers:
a: Removal (page 4-118)
b. Installation (page 4-120)
INITIAL SETUP
Tools
Materials/Parts
Bar, pry
Tape, teflon (item 20, appendix E)
Hammer, hand, ball-peen, 2-lb
Pliers, long round-nose
Personnel Required
Screwdriver, cross-tip, number two
Screwdriver, flat-tip, 3/16-inch
Two
Wrench, box-end, 1/2-inch
Wrench, box-end, 9/16-inch
Equipment Condition
Wrench, box-end, 11/4-inch
Wrench, box-end, 11/2-inch
Air reservoir drained (page 2-13).
Wrench, open-end, 9/16-inch
Wrench, open-end, 11/16-inch
Wrench, open-end, 7/8-inch
Wrench, open-end, 1-inch
Wrench, open-end, 11/16-inch
Wrench, open-end box, 5/8-inch
Wrench, pipe, 18-inch
ACTION
LOCATION
ITEM
REMARKS
NOT E
New air tubing is manufactured to required length from bulk items. For information on
manufacturing new tubing, go to appendix G.
Both lines are removed the same way. This task is for one; repeat for the other.
4-117