b. Installation.
1.
Using a floor jack or 12-ton jack, raise axle high enough so that wheel assemblies (3 and 2) can
be mounted on axle.
2.
Install wheel assemblies (3 and 2) and 10 nuts (1).
WARNING
If
flange
nuts
cannot
be
torqued,
at
first
opportunity
have
Organization
Maintenance
torque
flange
nuts
to
proper
specifications. See Item 3 under Installation. Periodically stop and
check flange nuts for tightness if not properly torqued initially. This
will cause the wheel assembly to separate, resulting in injury to
personnel and damage to equipment.
CAUTION
To insure secure seating of wheel assembly, see Appendix H-22 for
correct torquing sequence.
3.
Lower wheel assemblies (3 and 2) to the ground and torque 10 nuts (1) to 450–500 lb-ft (610–678
N•m) of torque.
c.
Follow-On Tasks.
1.
Remove all jacks/stands.
2.
Connect semitrailer to prime mover (if required).
3.
Raise landing legs (if required).
4.
Remove/store tire chocks and ground boards.
5.
Check air pressure for 115 psi (793 kPa).
6.
Insure proper torque has been applied to flange nuts.