0033-3/(4 blank)
TM 9-2330-335-14&P
0033
INSTALLATION - CONTINUED
NOTE
Tighten hubcap fasteners to 15 lb-ft (20.3 Nm).
3.
Install new gasket (Figure 1, Item 10) and hubcap (Figure 1, Item 11) onto hub (Figure 1, Item 3) using six new
lockwashers (Figure 1, Item 12) and screws (Figure 1, Item 13). Gasket should be dry.
WARNING
Do not get oil on mounting face of drum or wheel. Failure to comply may result in injury or death
to personnel.
NOTE
•
All flange nuts and studs are right-hand threads.
•
Apply two drops of oil between nut and flange.
•
Apply two drops of oil to last two or three threads at end of each stud.
•
Using oil, lightly lubricate pilots on hub to ease wheel and removal and installation.
4.
Seat brake drum (Figure 1, Item 14) onto hub (Figure 1, Item 3) using 10 wheel studs (Figure 1, Item 4) as guides. Do not
damage threads.
END OF TASK
FOLLOW-ON TASKS
00033
1.
Install tires and wheels (WP 0021).
2.
Connect semitrailer to prime mover.
3.
Raise landing legs.
4.
Remove/store chocks and ground boards.
5.
Road test to check for safe operation.
END OF TASK
END OF WORK PACKAGE