REPLACE BULKHEAD CONNECTION TO HEATER/FILTER SUPPLY HOSES
(M113A2 AND M1059 ONLY) — Continued
0603 00
5.
Install nipple (2) on hull. Secure with jamnut (7).
6.
Install tube (5) on nipple (2). Secure with nut (6) on tube.
7.
Install clamp (4) on tube (5). Align clamp with bulkhead weldnut. Secure with screw (3).
8.
Install fuel hose (1) on nipple (2).
FOLLOW-THROUGH STEPS
1.
Open heater fuel shutoff valve (see your -10).
2.
Connect battery ground lead (WP 0294 00).
3.
Bleed fuel line (WP 0599 00).
4.
Start heater (see your -10). Check all fittings for leaks. Turn heater off.
5.
Install power plant rear access panel (WP 0431 00 or WP 0432 00).
6.
Install right front floor plate (WP 0436 00 or WP 0438 00).
7.
Install heater duct (WP 0617 00 or WP 0623 00).
8.
Raise and lock ramp (see your -10).
9.
Stop engine (see your -10).
END OF TASK
0603 00-5/6 blank