TM 5-3895-372-20
CEMENT SYSTEM.
B-12.
SPRING TINE MAINTENANCE (Continued).
LOCATION/ITEM
ACTION
REMARKS
A.
INSPECTION (Continued).
2. Notched arm (4).
Check that arm can be
Adjust if necessary (Part C).
pressed down 3/4-1 in.
(19-25 mm) when shaft
link (3) is in notch.
B.
HAMMER REPLACEMENT.
CAUTION
Always check adjustment after replacing a hammer.
3. Shaft link (3).
Remove from notch.
4. Screw (5) and nut (7).
Unscrew and remove.
Remove
hammer (6).
5. Hammer (6).
Attach to spring tine with screw
(5) and nut (7).
Tighten.
C.
ADJUSTMENT.
6. Shaft link (3).
Try placing link in a different.
If this does not work, go to
notch of arm (4).
You should
Step 7.
be able to press arm down
3/4-1 in.
(19-25 mm) against
spring tension.
7. Shaft (9).
Turn with pipe wrench until
arm goes down 3/4-1 in. (19-
25 mm) against spring (8) when
shaft link (3) is in a notch.
8-34