TM 5-5420-202-20-2
TRANSMISSION MOUNTS (LEFT AND RIGHT) REPLACEMENT (Sheet 1 of 4)
PROCEDURE INDEX
PROCEDURE
PAGE
Removal
6-8
Cleaning and Inspection
6-10
Installation
6-10
TOOLS: Hammer
3-1/8 in. socket with 3/4 in. drive
T-slide handle with 3/4 in. drive
Diagonal cutting pliers
4 in. extension with 3/4 in. drive
Slip joint pliers
1-1/2 in. open end wrench
1-1/2 in. socket with 3/4 in. drive
Ratchet with 3/4 in. drive
3/4 in. socket with 1/2 in. drive
Ratchet with 1/2 in. drive
1-1/4 in. open end wrench
Bench vise
Torque wrench with 3/4 in. drive (0-600 lb-ft) (0-813 NŽm)
1/2 in. square drive bit screwdriver
Torque wrench with 1/2 in. drive (0-175 lb-ft) (0-237 NŽm)
SPECIAL TOOLS:
Resilient mount mechanical puller (Item 34, Chapter 3, Section 1)
SUPPLIES:
Dry cleaning solvent (Item 55, Appendix D)
Gloves (Item 69, Appendix D)
Lockwire (Item 61, Appendix D)
Goggles (Item 70, Appendix D)
Rags (Item 65, Appendix D)
PERSONNEL: Two
PRELIMINARY PROCEDURE:
Remove powerplant (page 5-2).
NOTE
The procedure described below applies to both the right and left transmis-
sion mounts.
Go on to Sheet 2
6-8