ARMY TM 9-1290-365-24&P
SECTION II. TECHNICAL SUPPORT REQUIREMENTS
SECTION CONTENTS
Subject
Page
Facilities .
...................................................................................................................................................
D-2
Test Equipment and Special Tools .
..........................................................................................................
D-2
Material Required.
.....................................................................................................................................
D-2
Fabricated Tools and Equipment.
.............................................................................................................
D-2
Mandatory Replacement Parts .
................................................................................................................
D-2
Repair Parts .
.............................................................................................................................................
D-2
Modifications .
............................................................................................................................................
D-2
D.2 TECHNICAL SUPPORT REQUIREMENTS.
D.2.1 Facilities.
There are no special facilities required to perform this procedure.
D.2.2 Test Equipment and Special Tools.
The test equipment and special tools required for the
maintenance of the M93 Muzzle Velocity System (MVS) transceiver are listed in the appropriate sections
for each assembly or subassembly.
D.2.3 Material Required.
The materials and other consumable items required for the general mainte-
nance of the M93 MVS transceiver are listed in the appropriate sections for each assembly or
subassembly.
D.2.4 Fabricated Tools and Equipment.
No fabricated tools or equipment are required to test and
maintain the M93 MVS transceiver at depot maintenance.
D.2.5 Mandatory Replacement Parts.
There are no mandatory replacement parts required during
overhaul of the MVS transceiver.
D.2.6 Repair Parts.
Refer to Appendix C of this manual for the depot level repair parts that may be
required dunng overhaul.
D.2.7 Modifications.
All current Modification Work Orders (MWOs) not installed must be applied to the
M93 MVS transceiver or its repairable subassemblies before returning the item(s) to stock. Refer to DA
PAM 25-30 for published MWOs. Engineering Change Proposals (ECPs) specified by the
contractor/procurement work directive (PWD) must also be applied during the overhaul of the item(s).
D-2