INSTALLATION - Continued
26.
Install propeller shaft (Figure 14, Item 6) on transfer case front output flange (Figure 14, Item 3) with eight
screws (Figure 14, Item 4) and locknuts (Figure 14, Item 5). Tighten locknuts 32 to 40 lb-ft (43
to
54
N·m).
27.
Install propeller shaft (Figure 14, Item 1) on transfer case input flange (Figure 14, Item 2) with four screws
(Figure 14, Item 8) and lockwashers (Figure 14, Item 7).
M7069DAA
3
4
5
6
7
8
2
1
Figure 14.
Transfer Case Cables Installation.
END OF TASK
FOLLOW-ON MAINTENANCE
1.
Install transfer case shift rod. (WP
0396)
2.
Install transfer case front axle engagement control valve. (WP
0388)
3.
Install transfer case interlock valve. (WP
0394)
4.
Install transfer case-to-forward rear axle propeller shaft. (WP
0402)
5.
Install wet reservoir. (WP
0451)
6.
Install spare tire (M923/A1/A2, M925/A1/A2, M929/A1/A2, and M930/A1/A2). (TM 9-2320-272-10)
7.
Adjust parking brake. (TM 9-2320-272-10)
8.
Fill transfer case to proper fluid level. (Volume 5, WP
0820)
END OF TASK
END OF WORK PACKAGE
TM 9-2320-272-23-3
0385