TM 9-2320-304-14&P
2-66
Operating Instructions (Cont)
2-9. LOAD HANDLING SYSTEM (LHS) (CONT).
CAUTION
To avoid equipment damage, visually check that hook arm cylinders have completed
full extension.
To avoid equipment damage, ensure that hook arm cylinders do not complete full
extension while operating at engine speeds above idle.
Ensure rail transport locking pins are disengaged before unloading flatrack. Rail
transport locking pins are used for rail transport only. Failure to comply may result
in damage to equipment.
NOTE
LHS OVER LOAD indicator will come on when hook arm cylinders are fully
extended and joystick is activated.
The amount of time to load and unload is controlled by engine speed. Engine speed
can be increased to 1,500 to maximum rpm to reduce loading and unloading times.
(7)
Move the joystick (8) to UNLOAD position and hold until hook arm cylinders (9) are fully
extended.