12-82.
TM 9-2320-361-20
This task covers:
a. Removal
c. Installation
b. Cleaning
INITIAL SETUP:
APPLICABLE MODELS
REFERENCES (TM)
M185A3, M109A3
TM 9-2320-361-10
MATERIAL/PARTS
TM 9-2320-361-20P
Fifty-four rivets
EQUIPMENT CONDITION
Fifty-four plugs
Parking brake set (TM 9-2320-361-10).
Tar (Appendix C, Item 29)
NOTE
Side rails on both sides of van body are removed and installed the
same. This task covers one side.
1. Drill fifty-four plugs (3) and rivets (2) out of side rail (4) and van wall (1).
2. Remove two side rails (4) from van wall (1).
Clean all tar out of rivet holes (5) and side rail (4).
NOTE
A sealer coat of hot tar must be applied to inside of rail in area of
rivet holes before installation.
Install two side rails (4) on van wall (1) with fifty-four new rivets (2) and plugs (3).
12-131