TM 9-2320-361-20
TM 9-2320-361-20
TM 9-2320-361-34
3-14. ENGINE OIL COOLER REPLACEMENT
(Contd)
I
b. Installation
1.
2.
3.
4.
5.
6.
7.
8.
Apply light coat of sealing compound to new gasket (18) and new gasket (11).
Install two new preformed packings (19), new gasket (18), oil cooler (10), new gasket (11), and
cover (17) on oil cooler housing (6), eleven studs (7), and stud (8) with eleven new lockwashers (15)
and nuts (16).
Install clamp (12) on stud (8) and cover (17) with new lockwasher (13) and nut (14).
Install washer (21) and injector line retainer clamp (5) on stud (20) with new lockwasher (4) and
nut (3).
Install three injector lines (2) on three injector pump ports (22) and injectors (9).
Install injector line (23) and dust cover (1) on injector pump port (22).
Install two clamps (24), washers (25), screws (26), and new locknuts (27) on injector line (23).
Install three dust covers (1) over three injector pump ports (22).
3-47