SHUTDOWN CRANE - Continued
NOTE
•
Operate control lever with light, even pressure.
•
TELESCOPE and HOIST control levers should be operated at same
time to keep hook block at least 2 ft. (0.61) from end of boom.
•
Crane movement from one lever may be slower than the other when
operating levers together.
4.
Move TELESCOPE control lever (4) to IN position to pull boom extensions (5) in and
move HOIST control lever (6) to UP position to reel in cable (7) until all boom
extensions (5) are fully retracted.
Figure 19.
5.
Operate SWING control lever (8) to position boom (9) parallel with outrigger beam
(10) on passenger side of vehicle.
CAUTION
Boom must rest on rest pad when transporting vehicle. If not, damage to
equipment may result.
6.
Move MAST control lever (11) to DOWN position to lower mast (12) until mast is
completely folded down.
TM 9-2320-428-10
0042
0042-21