RAISE AND LOWER LOAD - Continued
•
If electrical power fails during crane operation, move switch on
REMOTE CONTROL UNIT to SHUTDOWN position. Failure to
comply may result in injury or death to personnel.
CAUTION
•
Do not let cable become slack or cable may get tangled on drum.
•
Do not drag load sideways on ground or damage to crane may result.
1.
Operate SWING control lever (1) and center end of boom (2) directly over load.
6
1
3
2
4
5
Figure 17.
CAUTION
Release hook lock before connecting load hook to avoid damage to hook
lock.
2.
Operate HOIST control lever (3) to raise or lower cable (4) and connect load hook (5)
to load.
TM 9-2320-428-10
0042
0042-18