SHUT DOWN CRANE - Continued
4
18
11
13
14
16
15
17
3
10
Figure 23.
NOTE
•
Operate BOOM and HOIST control levers at the same time.
•
Crane movement from one lever may be slower than the other when
operating two levers together.
9.
Move BOOM control lever (10) to DOWN position until boom rests on mast pad (17)
and move HOIST control lever (3) to UP position to remove slack from cable (4).
STOW OUTRIGGERS
1.
Remove two retaining pins (1) from each outrigger pad (2).
TM 9-2320-431-10-1
0106
0106-25