TM-9-2330-324-14-P

TRAILER, CARGO: 1-1/2-TON, 2-WHEEL, M105A3

TECHNICAL MANUAL; OPERATOR’S, ORGANIZATIONAL, DIRECT SUPPORT, AND GENERAL SUPPORT MAINTENANCE MANUAL (INCLUDING REPAIR PARTS AND SPECIAL TOOLS LIST)

JULY 2002

  TM-9-2330-324-14-P - Page 195 of 350

TM 9-2330-324-14&P
0042 00-1
SAFETY CHAIN REPLACEMENT
0042 00
THIS WP COVERS:
Removal, Installation
INITIAL SETUP:
Maintenance Level
Tools and Special Tools
Organizational
Tool Kit, General Mechanic’s
Materials/Parts
Cotter Pin (Item 5, WP 0061 00)
REMOVAL
NOTE
There are two safety chains and they are removed the same way. This
procedure covers one safety chain.
The breakaway cable is connected to the left safety chain and must b e
disconnected before removing the left safety chain.
1.
Remove cotter pin (1), nut (2), flatwasher (3), screw (5), flatwasher (4), and safety chain (6). Discard
cotter pin.
2
3
1
4
6
5


Back to Top