TM 9-2330-335-14&P
0057-2
0057
REMOVAL
00057
1.
Remove 8 locknuts (Figure 1, Item 3), 16 washers (Figure 1, Item 2), and 8 bolts (Figure 1, Item 1) from stowage
box (Figure 1, Item 4). Discard locknuts.
2.
Remove stowage box (Figure 1, Item 4) from side panel brackets (Figure 1, Item 6).
Figure 1.
Stowage Box.
057
END OF TASK
INSTALLATION
00057
NOTE
Replacement of stowage box side panels is a Direct Support function (see WP 0070). See TM 9-237
for welding instructions.
Paint entire box before installation of nonmetallic seal if necessary.
1.
Place stowage box (Figure 1, Item 4) on side panel brackets (Figure 1, Item 6). Set on side, slide in box, and then
bolt.
2.
Install stowage box (Figure 1, Item 4), 8 bolts (Figure 1, Item 1), 16 washers (Figure 1, Item 2), and 8 new locknuts
(Figure 1, Item 3).
3.
Install new nonmetallic seal (Figure 1, Item 5) as needed onto exterior lip of storage box (Figure 1, Item 4).
END OF TASK