TM 9-2350-256-20-2
0311 00
UNIT MAINTENANCE
RECOVERY VEHICLE, FULL TRACKED: MEDIUM, M88A1
FENDERS AND RELATED PARTS REPLACEMENT
REMOVAL, INSTALLATION
INITIAL SETUP:
Tools and Special Tools
Tool kit, general mechanic’s (item 59, WP 0490 00)
Materials/Parts
Lockwashers (106) (item 640, WP 0491 00)
Lockwashers (10) (item 642, WP 0491 00)
Pins (10) (item 725, WP 0491 00)
Screws (10) (item 400, WP 0491 00)
Screws (10) (item 414, WP 0491 00)
Screws (96) (item 427, WP 0491 00)
Personnel Required
Mechanics (2)
Equipment Condition
Tow cables removed as required for clearance (see WP
0375 00)
Spade lowered (refer to TM 9-2350-256-10)
NOTE
The following procedures are the same for both left- and right-sides.
Removal
WARNING
Fenders can fall when screws are removed. Be sure to secure fenders.
1.
Remove front fender (1) by removing six screws (6) and six lockwashers (7).
2.
Remove each of four fenders (2) by removing eight screws (8) and eight lockwashers (9).
0311 00-1