TM 9-2350-277-20-3
ADJUST TOW START CONTROL CABLE ASSEMBLY — Continued
0390 00
2.
Push control assembly handle (4) to full in position. Move controllever(5)toobtain0
.00to0.06inch(0
.00to1.5mm)
clearance between contact surface of lever and transmission tow start button (6).
3.
Position two collars (2) against clevis pin (7) and tighten two setscrews (1).
FOLLOW-THROUGH STEPS
1.
Close power plant access door. See TM 9-2350-277-10.
END OF TASK
0390 00-2
Change 5