2. CONDENSOR INSTALLATION.
This task covers:
a.
Condensor Installation.
INITIAL SETUP
Models
All
Test Equipment
None
Special Tools
None
Supplies
Air Conditioner Condensor
Connector 2 Pin
(2) Socket Contact
(2) Seal
Grab Handle
(2) Flat Washer-3/8 in.
(6) Lockwasher-3/8 in.
(2) Screw-3/8-16 x 1 in.
(4) Plate
(4) Flange Screw-3/8-16 x 2 in.
Personnel Required
MOS 52C, Utilities equipment repairer (2)
References
None
Equipment Condition
None
Special Environmental Conditions
None
General Safety Instructions
None
a.
Condensor Installation.
1.
Install grab handle (1) on
condensor (2) with two screws (3),
lockwashers (4), and washers (5).
NOTE
If condensor does not have
connector installed on two wires,
perform Steps 2 through 12.
If condensor has connector
installed on two wires, go to
Step 13.
2.
From edge of condensor (2), cut
two wires (6 and 7) to
8 in. (203 mm).