INSTALLATION - Continued
9.
Coat two inner pivot pins (Figure 9, Item 7) with grease and install inner pivot pins (Figure 9, Item 7) on apron
(Figure 9, Item 5) and dozer blade (Figure 9, Item 4) with two washers (Figure 9, Item 9) and screws
(Figure 9, Item 6).
10.
Align cover (Figure 9, Item 1) on dozer blade (Figure 9, Item 4) and secure with two screws (Figure 9, Item 2),
washers (Figure 9, Item 3), and new locknuts (Figure 9, Item 8).
4
M0052HBF
5
4
2
3
1
3
2
8
8
6
9
7
Figure 9.
Inner Pivot Pins Installation.
END OF TASK
FOLLOW-ON MAINTENANCE
1.
Install dozer blade extensions or dozer cutting edge (TM 5-2350-262-20).
2.
Unblock front of vehicle (TM 5-2350-262-20).
END OF TASK
END OF WORK PACKAGE