INSTALLATION - Continued
6.
Connect wiring harnesses (Figure 4, Items 1 and 2) to connectors (Figure 4, Items 3 and 7).
NOTE
Apply sealing compound before performing Step (7).
7.
Install cover (Figure 4, Item 8) on junction box (Figure 4, Item 9) with eight screws (Figure 4, Item 6).
8.
Install cables (Figure 4, Items 4 and 5) on connectors (Figure 4, Items 3 and 7).
M10138DAA
1
2
3
4
6
5
9
7
8
10
12
11
13
7
Figure 4.
Electrical Load Center Conduit Installation.
END OF TASK
END OF WORK PACKAGE
TM 9-2320-272-23-4
0648
0648-4