INSTALLATION - Continued
6.
Connect wiring harnesses (Figure 4, Items 1 and 2) to connectors (Figure 4, Items 3 and 7).
NOTE
Apply sealing compound before performing Step (7).
7.
Install cover (Figure 4, Item 8) on junction box (Figure 4, Item 9) with eight screws (Figure 4, Item 6).
8.
Install cables (Figure 4, Items 4 and 5) on connectors (Figure 4, Items 3 and 7).
M10138DAA
1
2
3
4
6
5
9
7
8
10
12
11
13
7
Figure 4.
Electrical Load Center Conduit Installation.
END OF TASK