TM-9-2320-272-23-4

TRUCK, 5-TON, 6X6, M939, M939A1, AND M939A2 SERIES TRUCKS (DIESEL)

TECHNICAL MANUAL; FIELD MAINTENANCE MANUAL; VOLUME 4 OF 5

SEPTEMBER 2012

  TM-9-2320-272-23-4 - Page 562 of 1393

INSTALLATION
1.
Position conduit (Figure 3, Item 9) on van body (Figure 3, Item 5).
2.
Install coupling (Figure 3, Item 8) on conduits (Figure 3, Items 4 and 9) with two nuts (Figure 3, Item 7).
3.
Install coupling (Figure 3, Item 11) on conduit (Figure 3, Item 9) and load center (Figure 3, Item 3) with nut
(Figure 3, Items 6 and 10).
4.
Route wiring harnesses (Figure 3, Items 1 and 2) through conduit (Figure 3, Item 9) and load center
(Figure
3,
Item
3).
5.
Install cover (Figure 3, Item 13) on load center (Figure 3, Item 3) with six screws (Figure 3, Item 12).
M10284DAA
3
4
7
5
6
8
9
1
2
Figure 3.
Electrical Load Center Conduit Installation.
TM 9-2320-272-23-4
0648
0648-3


Back to Top